2023 Street Paving Program

Project Overview

Adams County and Brannan Sand and Gravel are scheduled to begin a significant street maintenance program, paving approximately 77 lane miles in three different areas of unincorporated Adams County at the beginning of July. The project's scope will include asphalt milling, patching, overlay and striping operations. Work at Area 1 will take place in Sherrelwood, paving over 20 streets in the neighborhood west of Interstate 25 and north of US Highway 36. Area 2 operatio¬ns will take place in two sections of E. 152nd Avenue between Interstate 76 and Imboden Road. Paving in Area 3 will occur in the neighborhood east of Hayesmount Road between streets E. 167th Place and E. 163rd Place. Please reference project maps for exact paving locations. 

Overview MapArea 1

Project Schedule

  • The project is set to begin in early July and is anticipated to be complete in October, 2023.
  • Normal working hours will be from 8 a.m. to 4 p.m., Monday through Friday. Crews will begin working in Area 1 in July.
  • Operations will transition to Area 2 and 3 in late August for the remainder of the project.

Project Update 

This project was completed Oct. 27, 2023.

Pecos St. Widening ProjectPecos St. Widening ProjectPecos St. Widening Project