ADA Five Areas Project
Project Overview
Americans with Disabilities Act improvements (curb, gutter, and sidewalks) in the following areas:
- Area 1: E. 68th Ave. - Washington St. to York St.
- Area 2: E. 66th Ave. - Washington St. to York St.
- Area 3: Steele St. - Niver Creek Tr. to E. 86th Ave.
- Area 4: E. 56th Ave. - Lincoln St. to Washington St.
- Area 5: E. 55th Ave. - Lincoln St. to Washington St.
Project Cost:
- Areas 1-4: $5,360,000
- Area 5: $680,000
Project Schedule
- Areas 1, 2, 4
Engineering Design: Complete - Area 3
Engineering Design: Mid 2021 - Areas 1 - 4
ROW Acquisition: 2021
Construction Schedule
One area per year 2021, 2022, 2023, or 2024
- Area 5: Complete