Project Overview
Project Location
(click to enlarge)
(click to enlarge)
Detour Routes
Click here to view the current map for detour routes.
Click here to view the current map for detour routes at Riverdale Regional Park.
How to Access Riverdale Regional Park
Please be advised that all traffic entering and exiting Riverdale Regional Park will be detoured through the Adams County Museum parking lot. Additionally, drop-in drone use is temporarily prohibited in the gravel parking lot north of the museum until the construction project is complete. The access detour will remain in place until further notice. We appreciate your patience and understanding during this time.
How to Access Riverdale Animal Shelter
During Phase 1 of construction, Park Blvd. will be closed at the intersection of Henderson Rd. and Park Blvd. Residents, staff, and animal management officers can access Riverdale Animal Shelter by using E. 120th Pkwy. Thank you for your patience during this time.
Project Updates
25-Apr | Exterior curb/gutter pour |
26-Apr | Exterior curb/gutter pour |
27-Apr | Handicap ramp pour |
28-Apr | Prep for median cover |
29-Apr | Pour median cover |
30-Apr | Asphalt Placement |
2-May | Asphalt Placement |
3-May | Asphalt Placement |
4-May | Asphalt Placement, Rip Rap installation |
5-May | Sign placement |
6-May | Sign placement |
9-May | Erosion Control |
10-May | Punchlist |
11-May | Punchlist |
12-May | Thermoplastic |
13-May | Thermoplastic |
14-May | Thermoplastic |
16-May | Parks sign replacement |
17-May | Asphalt Removal/Replace at Museum entrance |
18-May | Punchlist |
19-May | Punchlist |
20-May | Punchlist |
23-May | Irrigation, Electrical, Cultural Arts Project |
24-May | Irrigation, Electrical, Cultural Arts Project |
25-May | Irrigation, Electrical, Cultural Arts Project |
26-May | Irrigation, Electrical, Cultural Arts Project |
27-May | Irrigation, Electrical, Cultural Arts Project |
31-May | Irrigation, Electrical, Cultural Arts Project |
1-Jun | Irrigation, Electrical, Cultural Arts Project |
2-Jun | Irrigation, Electrical, Cultural Arts Project |
3-Jun | FINAL Walk with Adams County for acceptance |
Contact Information
If interested in receiving information and updates about the roundabout project, please contact Casey Watkins, Project Manager, at casey.watkins@elitesi.com or 720.402.5424.
For more information about the project, please contact Landon Stewart, Operations Manager, at landon.stewart@elitesi.com or 720.626.1587 or Fred Weisenborn, General Superintendent, at fred.weisenborn@elitesi.com or 720.557.5423.