Henderson Rd. – Park Blvd. Roundabout Project

Project Overview

Adams County will begin a road improvement project at the intersection of Henderson Rd. and Park Blvd. The focus of the project is to construct a roundabout and cultural arts project. The project has an estimated completion date of June 10, 2022. Weather impacts could affect the completion date.

Project Location

Henderson Road Roundabout Project

(click to enlarge)

RoundaboutRoundabout

(click to enlarge)

Detour Routes

Click here to view the current map for detour routes.

Click here to view the current map for detour routes at Riverdale Regional Park.

How to Access Riverdale Regional Park

Please be advised that all traffic entering and exiting Riverdale Regional Park will be detoured through the Adams County Museum parking lot. Additionally, drop-in drone use is temporarily prohibited in the gravel parking lot north of the museum until the construction project is complete. The access detour will remain in place until further notice. We appreciate your patience and understanding during this time.

How to Access Riverdale Animal Shelter

During Phase 1 of construction, Park Blvd. will be closed at the intersection of Henderson Rd. and Park Blvd. Residents, staff, and animal management officers can access Riverdale Animal Shelter by using E. 120th Pkwy. Thank you for your patience during this time.

Project Updates

25-Apr Exterior curb/gutter pour
26-Apr Exterior curb/gutter pour
27-Apr Handicap ramp pour
28-Apr Prep for median cover
29-Apr Pour median cover
30-Apr Asphalt Placement
2-May Asphalt Placement
3-May Asphalt Placement
4-May Asphalt Placement, Rip Rap installation
5-May Sign placement
6-May Sign placement
9-May Erosion Control
10-May Punchlist
11-May Punchlist
12-May Thermoplastic
13-May Thermoplastic
14-May Thermoplastic
16-May Parks sign replacement
17-May Asphalt Removal/Replace at Museum entrance
18-May Punchlist
19-May Punchlist
20-May Punchlist
23-May Irrigation, Electrical, Cultural Arts Project
24-May Irrigation, Electrical, Cultural Arts Project
25-May Irrigation, Electrical, Cultural Arts Project
26-May Irrigation, Electrical, Cultural Arts Project
27-May Irrigation, Electrical, Cultural Arts Project
31-May Irrigation, Electrical, Cultural Arts Project
1-Jun Irrigation, Electrical, Cultural Arts Project
2-Jun Irrigation, Electrical, Cultural Arts Project
3-Jun FINAL Walk with Adams County for acceptance

 

 

Remote video URL

Contact Information

If interested in receiving information and updates about the roundabout project, please contact Casey Watkins, Project Manager, at [email protected] or 720.402.5424.

For more information about the project, please contact Landon Stewart, Operations Manager, at [email protected] or 720.626.1587 or Fred Weisenborn, General Superintendent, at [email protected] or 720.557.5423.